TriMark USA's Bryan Musgrove Outlines Three Equipment Rollout Practices

Katarina VukovicNovember 1, 20265 min read3 views

At a glance

  • A location playbook, manufacturer-driven schedule and consolidated packaging can help restaurant brands prepare for new-menu equipment installations, according to TriMark USA's Bryan Musgrove.
  • Bryan Musgrove of TriMark USA outlines a three-part approach to equipment rollouts for new menu items: a location-by-location playbook, a schedule built around manufacturer lead times and packaging consolidated by site. He cites toasters for toasted sandwiches and holding cabinets for macaroni and cheese as examples of planning needs.
A conceptual commercial kitchen scene shows toasters, holding cabinets, pans, scoops and consolidated shipping cartons arranged for a multi-location equipment rollout.

Equipment rollouts for new menu items can run into electrical limits, space constraints and delivery complications before the item is served. Bryan Musgrove, divisional senior director on national accounts for TriMark USA, says careful planning across locations can make the process more seamless. He outlined three practices based on TriMark's work with restaurant brands.

Build a location-by-location playbook

Musgrove recommends creating a rollout playbook that distinguishes sites that can accommodate new equipment as-is from those that need additional support. TriMark worked with a brand that needed new toasters to add toasted sandwiches to an existing breakfast lineup of biscuits and wraps. Some locations, Musgrove says, have no remaining electrical capacity. A small mall or urban location may lack counter space for a toaster, requiring the brand to create space by adding shelving or another table. Those changes can affect workflow, making it important to identify them before installation.

The playbook, according to Musgrove, breaks down which locations are plug-and-play and which require extra work. That gives the rollout a clearer view of site readiness instead of treating every location the same.

Schedule around manufacturer lead times

The rollout schedule should be driven by how long the equipment manufacturer needs to produce and deliver the units. Musgrove describes a manufacturer that might say it can produce 200 units, but the relevant question is how long production will take. At 10 units a week, he says, that would take 20 weeks. A manufacturer might also have inventory for the first 50 units before needing to order parts from overseas, adding eight weeks before the remaining units can be completed.

For a menu item tied to a seasonal or occasion-based marketing campaign, Musgrove says brands should work backward from the desired launch date to build a timeline that can be achieved. The schedule needs to reflect production sequencing and parts availability, not just the target launch date.

Consolidate packaging by location

Delivery planning is another part of the rollout. Rather than shipping smaller wares directly to each location in their original boxes, Musgrove suggests asking the dealer to consolidate and repackage items into one package per location. TriMark worked with a brand adding macaroni and cheese to its sides lineup. The addition required visual holding cabinets, pans and serving scoops in varying sizes. TriMark combined the items into one package per location, including instructional materials and exterior labeling so managers knew exactly what they were receiving when it arrived.

Musgrove says following these practices—from deciding which locations need more support to simplifying deliveries—can help ensure a smooth rollout. If the plan works as intended, the new menu item can generate attention and increase traffic. The approach is less about a single piece of equipment than about coordinating site readiness, production timing and delivery details across the system.